Construction Schedule Report: On
December 12, project managers presented a Great American Ball Park
construction schedule update to the Hamilton County Commissioners at the
weekly Commission meeting. Key Schedule Items: o
The ball park remains on target for an
April 2003 Opening Day. o
The Cincinnati Reds administration
building remains on target for a November 2002 occupancy. o
Phase 2 demolition, the demolition of the
remainder of Cinergy Field, is scheduled to commence in November of 2002. o
Phase 2 construction of Great American
Ball Park, including the Reds Hall of Fame, Crosley Terrace and completion
of the ball park grounds is on target for an April 2004 (Opening Day 2004)
completion. |
|
·
SBE
Numbers Remain Strong: Project
managers also released a report outlining the level of Small Business
Enterprise participation in the Great American Ball Park project.
As of October 31, 2001, a total of 26.8% of all contracted work had
been committed to small businesses, which includes any minority- and
women-owned businesses that also are classified as small businesses.
A further breakdown shows that 11.9% of contracts went to
minority-owned businesses and 3.9% to women-owned enterprises. |
|
·
Safety
Update:
Through October 31, only two lost work
day incidents had been reported for the construction of Great American
Ball Park and related projects. Even
with these incidents, the project lost work day incident rate stands at
1.0, well below the national average of 5.4.
|
|
·
Workforce Breakdown of Project: Commissioners
also were presented with workforce breakdowns by race and gender for
contracts awarded through October 31, 2001.
Percentages were as follows: 83% White, 14% African-American, 2%
"other," and 1% Hispanic; and 95% male, and 5% female. |
For more
information Bill Wherle or Debra DeCourcy,
APR
on next week’s ball park
Dan Pinger Public Relations, Inc.
activity, contact:
(513) 564-0700
###