July 19, 2002

Play-By-Play

 

Construction Schedule Report: On July 15, project managers presented a Great American Ball Park construction schedule update to the Hamilton County Commissioners at their weekly staff meeting.

Key Schedule Items:
° Ballpark is 70% complete and remains on target for Opening Day 2003. (Phase 1 – substantial completion)
° Ballpark plaza and parking remains on target for April 2004. (Phase 2)
° The Cincinnati Reds Hall of Fame is on target for a summer 2004 completion.
 
SBE Numbers Remain Strong: Project managers also released a report outlining the level of Small Business Enterprise participation in the Great American Ball Park project. As of May 31, 2002, a total of 26.8% of all contracted work had been committed to small businesses, which includes any minority- and women-owned businesses that also are classified as small businesses. A further breakdown shows that 11.8% of contracts went to minority-owned businesses and 4.2% to women-owned business enterprises.
 
Safety Update: Through May 31, only four lost workday incidents were reported for the construction of Great American Ball Park and related projects. Even with these incidents, the project lost workday incident rate stands at 1.1, well below the national average of 5.4. The project has received numerous accolades from the Occupational Safety & Health Administration (OSHA) regarding safety on the project.
 

Community Display Schedule: The Great American Ball Park traveling display, featuring photographs, renderings and riverfront development information, will be on display at the Scripps Center, 312 Walnut Street, July 23-August 6.