Work in
Progress: Crews
continue to make notable progress in all areas of the ball park. Following
are a few of the activities currently underway: |
|
o
Initial Pouring Near Completion: Concrete placement
for the main ball park superstructure is close to completion. Crews will
then need to finish pouring concrete for topping slabs, as well as slabs
on grades and supported slabs. |
|
o
Light Tower work underway: Work has begun on the base
sections along the north side of the ball park. These triangular metal
structures mark the initial sections of the towers, which will support the
lighting that will eventually illuminate Great American Ball Park. |
|
o
Steel for
Administration Building Erected: The
first steel columns have been erected for the administration building. The
skeleton of the building’s superstructure is seeing its “first pass”
and will now progress onto the upper levels. These columns will also be
the basis from which the Spirit of Baseball relief sculpture is
supported. |
|
Fun Fact: Each steel portal column weighs approximately 2,700 pounds. Altogether, the four steel columns are the same combined weight as nearly 1,000 holiday turkeys! |
|
·
Traveling
Display Locations December 3-13:
Public Library of Cincinnati & Hamilton County Main Branch, 800 Vine St., Cincinnati |
For more information
Bill Wherle or Debra DeCourcy, APR
on next week’s ball park Dan Pinger Public Relations, Inc.
activity, contact: (513) 564-0700
# # #