|
|
·
Year in Review: The future home of the
Reds has grown by leaps and bounds over the past year. The first full
calendar year of construction has seen the framework of Great American
Ball Park grow right before our eyes. This issue of the Play-By-Play
focuses on project work accomplished in 2001. |
|
·
Steel Work: Steel workers have been busy since first installing steel in
July. Crews installed structural steel for the first time on July 23. More
than 10,000 tons of steel was installed during 2001, and installation will
continue through April 2002. Steel work has progressed in the following
areas: o
The steel structure
for the Administration Building is well underway. o
Triangular metal
structures were put into place and will form the base of the light towers. o
Huge steel portal
frames were installed alongside the third base line. The frames will form
the vast concourses that will eventually hallmark Great American Ball
Park. o
Steel installation
has progressed far enough west to shape “the Gap,” the opening that
aligns with Sycamore Street, which will open up the ball park allowing
fans inside a view of the city and pedestrians outside a view of the
field. |
|
·
Concrete Work:
Workers began placing concrete for the ball park’s foundation in
early February. This work signified the beginning of an extensive work
schedule that included: o
The first elevated
concrete pour in May. The first pour consisted of 8,000 square feet of
concrete elevated approximately 10 feet by support beams. The pour
constituted the mezzanine level of the northeast parking garage. o
The final pieces of
the floodwall and the outer protective walls. o
Concrete for
flooring has been poured beneath the left field seating structures. o
Pre-cast concrete
seating structures were installed alongside the third base line and the
lower seating levels. Elevated slabs also were poured along the third base
line, as well as for topping and supporting structures. o
Crews completed
installation of structural concrete that will support Crosley Terrace, the
main entrance to the ball park. o
Installation of the
left field wall. This wall reaches from the seating area to the playing
surface. It will house the out-of-town scoreboard. o
Much of the main
parking area on multiple levels of the Main Parking garage. There will be
a total of 850 spots within the park. |
|
·
Interior/Utilities
Work: Ductwork, air
handling, and electric groundwork have begun within the ball park. Crews
also have been working diligently on the main media access area and the
visitors’ clubhouse as well. |
For more
information Bill Wherle or Debra DeCourcy,
APR
on next week’s ball park
Dan Pinger Public Relations, Inc.
activity, contact:
(513) 564-0700
###