|
·
Preview 2002: This year will be a big
one for construction of Great American Ball Park. By the end of 2002 the complex will look and feel like a
baseball park. This issue of Play-By-Play
looks ahead to 2002. |
|
·
Steel Installation:
The steel
superstructure of the ball park will be completed in 2002.
By the end of winter, all of the steel for the second deck will be
installed. Soon after, crews
will begin another pass with the cranes to install the upper decks and
supports. Another pass will
install the roofing/canopy in the spring.
This
week crews successfully “topped off” the administration building,
marking the completion of the steel superstructure for the first of the
“out-buildings” to be constructed on the north side of the ball park
complex. Erection
of the light towers on their already constructed bases will begin later
this winter. By mid-spring
installation will be complete with the tops of the towers reaching 228
feet above the playing surface. |
|
·
Concrete Work:
The placing of concrete also will continue at a blinding pace.
Pre-cast concrete seating structures will be installed in each of
the decks as they are completed. The
placing of concrete inside completed steel structures will form the floors
and walls of the buildings in the complex. |
|
·
Utilities &
Interiors: All
deep utilities will be completed this month.
Utility crews will then focus their efforts indoors.
Heating and cooling systems, electrical systems and plumbing, which
were installed in 2001, will be completed, allowing portions of the
complex to be occupied by year’s end.
The Reds are slated to move in to the new administration building
in November. |
|
·
Façade & Finish
Work:
Installation of the brick façade
will begin on portions of the ball park by the end of winter.
The first of the brick work will be applied to the administration
building. A majority of the
facade and finish work for the exterior of all of the existing buildings
will be completed by the beginning of 2003.
Perhaps
the most noticeable finishing work to begin in 2002 will be the
installation of seats. Installation
of the 42,000+ seats will begin late in the summer of 2002, with a
completion in early 2003. Unlike Cinergy Field, which featured color-coded
seats, all seats in Great American Ball Park will be red. |
|
·
Demolition:
Shortly after the completion of the Reds’ 2002 season, final
demolition of Cinergy Field will begin. |
For more
information Bill Wherle or Debra DeCourcy,
APR
on next week’s ball park
Dan Pinger Public Relations, Inc.
activity, contact:
(513) 564-0700
###