 | Home Run Feature – Crews continue to work on the
Cincinnati Reds home run celebration feature, located between the Batter’s
Eye and the Sun/Moon Deck. Workers have drilled holes into the concrete
and are installing the steam-blowing pipes.
|
 | Backstop – A net backstop has been installed behind home plate. The backstop
is in place to ensure that balls fouled back do not strike the fans seated
behind home plate.
|
 | Sound System and Video Board – Crews have begun testing the sound system
in the concession areas and around the lower bowl of the ballpark. Workers
also are testing the digital video board located on the main scoreboard.
|
 | Field wall pads – Workers continue to place the green padding along the
field walls.
|
 | Broadcast booths – Work on the press box is near completion. The separate
booths for home and visitor television and radio broadcasts are beginning
to take shape.
|
 | Clubs – Work continues on the Riverfront Club and Club 4192. Crews are
currently constructing the chef stations and bars.
|